June 4, 2021
Starting Monday, June 7, Howard Street from Frances Street to State Road 23 will close as work begins on the Howard Street & Corby Boulevard Streetscape Improvement Project. The intersection at Howard and Eddy streets will also be closed at the same time. The project includes new curbs, sidewalks, pavement, storm sewers and streetlights along the two streets. The anticipated completion date for this project is Thursday, July 15, weather permitting.
During construction, there will be two phases of street closures:
- Howard Street from Frances Street to State Road 23 and the Howard and Eddy streets intersection will be closed from June 7 to June 28, weather permitting.
- Corby Boulevard from Frances Street to South Bend Avenue will be closed from June 29 to July 15, weather permitting.
###