April 10, 2020
Starting Monday, April 13, Ameritech Drive from Cleveland Road to Carbonmill Drive will be milled and resurfaced with asphalt. During construction, the road will remain open but traffic will be restricted. The anticipated completion date is Friday, April 17, weather permitting.
Ameritech Drive is one of five roadways that will be paved as a result of securing additional funding through the state of Indiana’s Community Crossings Matching Grant in Fall 2019. The other roadways being paved are:
- Ironwood Drive from Ireland Road to city limits
- Miami Street from Ireland Road to Widener Lane
- Miami Street from Calvert Street to Lincoln Way East
- Olive Street from Elwood Avenue to Lincoln Way West
In addition to the grant funded paving, the City is currently finalizing approximately 15 lane miles of neighborhood streets that will be paved in 2020. The list is expected to be completed in coming days with paving activity starting in the next few weeks.
###